Phase 3 of Hoggs Hollow Stormwater and Road Improvement Project Begins!
As I mentioned in April, the first and second phase of the city’s $24-million Hoggs Hollow stormwater management and road improvements project are complete and construction on the third phase has just begun.
Construction is starting soon on the following streets:
- Donwoods Drive from Knightswood Road to Donino Avenue;
- Donwoods Grove;
- Winton Road;
- Plymbridge Road from the bridge to Donwoods Drive; and,
- Donwoods Drive from Donino Avenue to Ivor Road.
The work involves storm sewer installation and road reconstruction. Phase IV is set to get underway in the second half of 2014.
See the construction notice below for more information.
For more information about any aspect of the project, you can contact Manveer Ramburrun, the Project Engineer, at mrambur@toronto.ca or (416) 395-1112.